    PANCHESHWAR MULTIPURPOSE PROJECT

    Publish Date: January 9, 2023

    Pancheshwar Development Authority (PDA)

    India and Nepal had signed a Treaty known as Mahakali Treaty in February, 1996. Implementation of Pancheshwar Multipurpose Project is the centerpiece of the Mahakali Treaty. Required field investigations for the Pancheshwar Multipurpose Project were completed by a Joint Project Office (JPO-PI) in 2002 (except for some confirmatory tests). But mutually acceptable DPR of Pancheshwar Project could not be finalized due to differences on certain contentious issues. For further details on Mahakali Treaty 1996,Mahakali Treaty(enclosed)(PDF 35.33KB)

    During the 3rd meeting of Joint Committee on Water Resources (JCWR) held in September-October 2008 at Kathmandu (Nepal), it was decided to set up Pancheswhar Development Authority (PDA) at the earliest for the development, execution and operation of Pancheshwar Multipurpose Project.

    The constitution of the Pancheshwar Development Authority has been notified vide Office Memorandum no. Z-14012/3/2013-Ganga dated 07.08.2014. For Terms of Reference (TORs),please click-TORs enclosed(PDF 232KB)

    Eight meetings of the Governing body of Pancheshwar Development Authority have been held so far.

    Detailed Project Report of Pancheshwar multipurpose Project- The draft final DPR of the project has been submitted by M/s WAPCOS in November 2016.At present the finalization of Detailed Project Report (DPR) of the project is underway.